Question

1 Approved Answer

Find the minimum possible time of the project and the cost associated with this. Predecessor Normal Crash time Normal time Crash cost Activity activity

Find the minimum possible time of the project and the cost associated with this. Predecessor Normal Crash time Normal time Crash cost Activity activity cost A 10000 15000 B 15000 21000 C A 4 20000 24000 D 1 7000 7000 B. 2 1 8000 15000 C.D 3. 10000 16000 12000 36000

Step by Step Solution

3.44 Rating (151 Votes )

There are 3 Steps involved in it

Step: 1

Answer Solution Selution 2 4 Paths ACF11 BDF 14 B EG 16 Critical path Activity pre dere... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Elementary Linear Algebra with Applications

Authors: Howard Anton, Chris Rorres

9th edition

471669598, 978-0471669593

More Books

Students also viewed these Accounting questions

Question

Find a, b, c and d if (a) (b) (c) (d) a b b-c 3 1 2 2

Answered: 1 week ago

Question

Find a, b, c and d so that 7 7

Answered: 1 week ago

Question

Find the derivatives of the function. 9 cot sin t t

Answered: 1 week ago