Finish the following variance report with the information given Commitments - salaries: $-315,587, grants: $100,213, O&M: $45,856 Projections - salaries: $-52,000, grants: $410,213, O&M: $14,856
Finish the following variance report with the information given
Commitments - salaries: $-315,587, grants: $100,213, O&M: $45,856
Projections - salaries: $-52,000, grants: $410,213, O&M: $14,856
Annual budget | YTD expenditures | YTD commitments | Projected expenditures | Year end projection | year end % variance | |
Salaries | 525,000 | 152,347 | ||||
Grants | 1,250,000 | 785,625 | ||||
O&M | 333,000 | 115,478 | ||||
total | 2,108,000 | 1,053,450 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started