Fisck Construction began a construction project in 2016. The contract price was $1,300,000 and estimated costs were $1,100,000. Data for each year follow: 2016 2017

Fisck Construction began a construction project in 2016.
The contract price was $1,300,000 and estimated costs were $1,100,000.
Data for each year follow:
2016 2017 2018
Costs incurred during the year $ 250,000 $ 600,000 $ 210,000
Estimated costs to complete $ 850,000 $ 230,000

0

Partial billings $ 400,000 $ 600,000 $ 300,000
Collections $ 385,000 $ 610,000 $ 305,000
Required:
Assuming Fisck satisfies its performance obligation over time, determine:
1. The balance of Construction in Progress at the end of 2016.
2. How the net amount for construction in progress inventory should be reported on the 2017 balance sheet.
3. The gross profit for 2018.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Dyslexia A Practitioners Handbook

Authors: Gavin Reid

5th Edition

1118980107, 9781118980101

More Books

Students also viewed these Accounting questions

Question

How is the NDAA used to shape defense policies indirectly?

Answered: 1 week ago