Fitness Bands Corporation gathered the following information for Job #928: Standard Total Cost Actual Total Cost Direct materials Standard: 2,100 pints at $4.00/pint Actual: 2,600
Fitness Bands Corporation gathered the following information for Job #928: Standard Total Cost Actual Total Cost Direct materials Standard: 2,100 pints at $4.00/pint Actual: 2,600 pints at $6.50/pint $8,400 $16,900 What is the direct materials price variance? A. $6,500 favorable B. $6,500 unfavorable O C. $5,250 favorable D. $5,250 unfavorable