Five customers brought in computers to be repaired to a small shop. Estimated repair times (in days) and dates promised are given below. Due dates
Five customers brought in computers to be repaired to a small shop. Estimated repair times (in days) and dates promised are given below. Due dates were set based on available technicians; however, one technician had a medical emergency and will be unavailable for at least two weeks, so processing times were adjusted.
Customer Job | 1 | 2 | 3 | 4 | 5 |
Processing Time (Days) | 4 | 5 | 1 | 7 | 3 |
Due Date (Days) | 3 | 5 | 2 | 10 | 6 |
Use the EDD rule to determine the EDD sequence.
- The EDD sequence, sorted by customer job is 4-1-2-3-5
- The EDD sequence, sorted by customer job is 1-2-3-4-5
- The EDD sequence, sorted by customer job is 3-1-2-5-4.
- The EDD sequence, sorted by customer job is 3-1-4-2-5
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started