Question
1 Approved Answer
Five days after the work begins (mobilization and site clearing), the owner (Town of Somewhere) issues a stop work order. 2 days later, He asks
Five days after the work begins (mobilization and site clearing), the owner (Town of Somewhere) issues a "stop work" order. 2 days later, He asks the contractor to proceed. The contractor asks for a s