Five jobs are ready for processing at time zero through a workstation. The details regarding the processing time and the due date of completion are
Five jobs are ready for processing at time zero through a workstation. The details regarding the processing time and the due date of completion are provided in the following table.
Job | Processing Time (days) | Days Due from Today |
A | 11 | 35 |
B | 10 | 39 |
C | 7 | 34 |
D | 8 | 42 |
E | 12 | 40 |
Using the shortest processing time (SPT) rule, it can be concluded that the average tardiness for the five jobs is:
| |||
| |||
| |||
|