Five jobs are ready for processing at time zero through a workstation. The details of the processing time and the due date of completion is

Five jobs are ready for processing at time zero through a workstation. The details of the processing time and the due date of completion is provided in the following table.
Job
Processing Time (days)
Due Date (days)
1
11
15
2
5
10
3
2
4
4
3
5
5
7
23
Using the shortest processing time (SPT) rule, it can be concluded that the average flow time for these five jobs is _____.
a. more than 14 but less than or equal to 16 days.
b. more than 8 but less than or equal to 10 days.
c. more than 12 but less than or equal to 14 days.
d. more than 10 but less than or equal to 12 days.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic Project Management Made Simple

Authors: Terry Schmidt

2nd Edition

1119718171, 978-1119718178

More Books

Students also viewed these General Management questions