Question

1 Approved Answer

Five samples of size 5 were taken from a process. A Range chart was developed that had LCLR = 0 and UCLR = 5.50. Similarly,

Five samples of size 5 were taken from a process. A Range chart was developed that had LCLR = 0 and UCLR = 5.50. Similarly, a Process Average chart was developed using the measurements from the five samples, with LCLx = 25.0 and UCLx = 40.0. The ranges for each of the five samples were 3.75, 2.42, 4.75, 2.04, and 5.80, respectively. The values of the sample average for each sample were 29.5, 27.3, 37.4, 26.1, and 28.9, respectively. What can you tell management from this analysis?

Group of answer choices

The process variability is out of control

The process average is out of control

Both the process variability and the process average are out of control

We cannot tell if the process variability or the process average is out of control

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Manufacturing Planning And Control For Supply Chain Management

Authors: F. Robert Jacobs, William Berry, David Clay Whybark, Thomas Vollmann

6th Edition

0073377821, 9780073377827

More Books

Students also viewed these General Management questions

Question

Discuss attention and its role in message processing.

Answered: 1 week ago