Fizzy-Lift has a new facility for production of its bottle filling machine. The firm has gone through a preliminary manufacturing period and believes that it
Fizzy-Lift has a new facility for production of its bottle filling machine. The firm has gone through a preliminary manufacturing period and believes that it is experiencing an 88% learning curve. The 200th unit required 1.4 labor hours for an assembly activity. Estimate the comparable time for the 500th unit