Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Flapjack Corporation had 7,849 actual direct labor hours at an actual rate of $12.10 per hour. Original production had been budgeted for 1,100 units, but
Flapjack Corporation had 7,849 actual direct labor hours at an actual rate of $12.10 per hour. Original production had been budgeted for 1,100 units, but only 975 units were actually produced. Labor standards were 7.8 hours per completed unit at a standard rate of $13.15 per hour.
The direct labor rate variance is
a.$8,241.45 unfavorable
b.$8,241.45 favorable
c.$3,618.88 unfavorable
d.$3,618.88 favorable
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started