Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Flapjack Corporation had 7,944 actual direct labor hours at an actual rate of $12.00 per hour. Original production had been budgeted for 1,100 units, but
Flapjack Corporation had 7,944 actual direct labor hours at an actual rate of $12.00 per hour. Original production had been budgeted for 1,100 units, but only 993 units were actually produced. Labor standards were 7.3 hours per completed unit at a standard rate of $12.75 per hour. Round your answer to the nearest cent. The direct labor time variance is
a. $5,942.11 unfavorable b. $5,942.11 favorable c. $8,862.53 unfavorable d. $8,862.53 favorable
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started