Flapjack Corporation had 7,992 actual direct labor hours at an actual rate of $12.41 per hour. Original production had been budgeted for 1,100 units,
Flapjack Corporation had 7,992 actual direct labor hours at an actual rate of $12.41 per hour. Original production had been budgeted for 1,100 units, but only 999 units were actually produced. Labor standards were 7.2 hours per completed unit at a standard rate of $12.75 per hour. Round your answer to the nearest cent. The direct labor time variance is Oa. $2.701.30 unfavorable Ob. $2.701.30 favorable Oc. $10.189.80 unfavorable Od. $10.189.80 favorable i
Step by Step Solution
There are 3 Steps involved in it
Step: 1