Flapjack Corporation had 8,000 actual direct labor hours at an actual rate of $12.38 per hour. Original production had been budgeted for 1,100 units, but
Flapjack Corporation had 8,000 actual direct labor hours at an actual rate of $12.38 per hour. Original production had been budgeted for 1,100 units, but only 1,000 units were actually produced. Labor standards were 7.2 hours per completed unit at a standard rate of $12.75 per hour. Round your answer to the nearest cent.
The direct labor time variance is
a.$3,000.00 unfavorable
b.$3,000.00 favorable
c.$10,200.00 unfavorable
d.$10,200.00 favorable