Flexible Budgeting and Variance Analysis I Love My Chocolate Company makes dark chocolate and light chocolate. Both products require cocoa and sugar. The following planning

Flexible Budgeting and Variance Analysis

I Love My Chocolate Company makes dark chocolate and light chocolate. Both products require cocoa and sugar. The following planning information has been made available:

Standard Amount per Case
Dark Chocolate Light Chocolate Standard Price per Pound
Cocoa 10 lbs. 7 lbs. $5.10
Sugar 8 lbs. 12 lbs. 0.60
Standard labor time 0.4 hr. 0.5 hr.

Dark Chocolate Light Chocolate
Planned production 5,400 cases 12,000 cases
Standard labor rate $15.50 per hr. $15.50 per hr.

I Love My Chocolate Company does not expect there to be any beginning or ending inventories of cocoa or sugar. At the end of the budget year, I Love My Chocolate Company had the following actual results:

Dark Chocolate Light Chocolate
Actual production (cases) 5,100 12,500
Actual Price per Pound Actual Pounds Purchased and Used
Cocoa $5.20 139,200
Sugar 0.55 186,000
Actual Labor Rate Actual Labor Hours Used
Dark chocolate $15.00 per hr. 1,860
Light chocolate 16.00 per hr. 6,410

Required:

1. Prepare the following variance analyses for both chocolates and the total, based on the actual results and production levels at the end of the budget year:

a. Direct materials price variance, direct materials quantity variance, and total variance.

b. Direct labor rate variance, direct labor time variance, and total variance.

Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.

a. Direct materials price variance $
Direct materials quantity variance $
Total direct materials cost variance $
b. Direct labor rate variance $
Direct labor time variance $
Total direct labor cost variance $

2. The variance analyses should be based on the amounts at volumes. The budget must flex with the volume changes. If the volume is different from the planned volume, as it was in this case, then the budget used for performance evaluation should reflect the change in direct materials and direct labor that will be required for the production. In this way, spending from volume changes can be separated from efficiency and price variances.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions

Question

Detailed note on the contributions of F.W.Taylor

Answered: 1 week ago