Flores Manufacturing, Inc., is moving to kanbans to support its electronic - board assembly lines. Determine the size of the kanban for subassemblies and the

Flores Manufacturing, Inc., is moving to kanbans to support its electronic-board assembly lines. Determine the size of the kanban for subassemblies and the number of kanbans needed.
Setup cost
$21
Annual holding cost subassembly
$150 per subassembly
Daily production
550 subassemblies
Annual usage
37,500(=50 weeks\times 5 days each\times daily usage of150subassemblies)
Lead time
3 days
Safety stock
1day's production of subassemblies
Part 2
The kanban size is 104104(round your response to the nearest whole number).

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Engineering Risk Management

Authors: Genserik Meyer, Thierry, Reniers

3rd Edition

311066531X, 978-3110665314

More Books

Students also viewed these General Management questions