Florican built new equipment in 2020. Construction began on 2/1 and ended on 12/1/2020. Florican paid $7,348,000 on the day construction began, $4,408,800 on 4/1,
Florican built new equipment in 2020. Construction began on 2/1 and ended on 12/1/2020. Florican paid $7,348,000 on the day construction began, $4,408,800 on 4/1, and $8,817,600 on 6/1. What were weighted average expenditures for the project? (A 24)
$5,388,533 | ||
$13,471,333 | ||
$15,185,867 | ||
$20,574,400 |