Flounder Construction Company began work on a $417,400 construction contract in 2020. During 2020, Flounder incurred costs of $267,500, billed its customer for $201,500, and

Flounder Construction Company began work on a $417,400 construction contract in 2020. During 2020, Flounder incurred costs of $267,500, billed its customer for $201,500, and collected $176,000. At December 31, 2020, the estimated additional costs to complete the project total $157,575.

Prepare Flounder’s journal entry to record profit or loss, if any, using

(a) the percentage-of-completion method and

(b) the completed-contract method.

Step by Step Solution

3.53 Rating (156 Votes )

There are 3 Steps involved in it

Step: 1

Answer a Total eastimated cost of contract 26750015... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Intermediate Accounting Reporting and Analysis

Authors: James M. Wahlen, Jefferson P. Jones, Donald Pagach

2nd edition

9781305727557, 1285453824, 9781337116619, 130572755X, 978-1285453828

More Books

Students also viewed these Accounting questions

Question

Describe the five-step decision-making process?

Answered: 1 week ago