Following are activities, precedence relationships, and task times for a number of tasks. Task Task Time ( days ) Preceding Task A 5 None B
Following are activities, precedence relationships, and task times for a number of tasks.
Task Task Time days Preceding Task
A None
B A
C A
D B
E C
F D
G E
H D
I C
J I, F
K G J
L H K
M L
a Construct a precedence diagram.
b Compute early and late times.
c Compute the slack for each task.