Following are simplified job cost sheets for three custom jobs at the end of June for Johnsons Patios. Job Number 502 Materials $ 35,000 Labor

Following are simplified job cost sheets for three custom jobs at the end of June for Johnsons Patios.

Job Number 502

Materials

$ 35,000

Labor

10,000

Overhead

3,600

Job Number 503

Materials

$ 72,000

Labor

28,500

Overhead

10,260

Job Number 504

Materials

$ 56,000

Labor

43,000

Overhead

15,480

All jobs were started in June. Overhead is applied with a predetermined rate based on direct labor cost. Jobs 502 and 503 were finished in June, and Job 504 will be finished in July.

5a. What was the total cost of direct materials requisitioned in June? Show your work.

5b. How much total direct labor cost was incurred in June? Show your work.

5c. How much total cost is transferred to Finished Goods Inventory in June? Show your work.

5d. Show your work and create two T-accounts below.

i. Post the applied overhead for Job 502 and 503 to T-accounts you create below.

ii. Next, post the actual overhead to the appropriate account: Actual Overhead for Job 502 is $4,000 and for Job 503 is 9,980.

iii. Describe the impact of the remaining balance for Job 502 and Job 503.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started