Question
Following information of the manufacturing unit is made available to you for the month of July 1996. BUDGET DATA Units 1000 3 kg per
Following information of the manufacturing unit is made available to you for the month of July 1996. BUDGET DATA Units 1000 3 kg per unit @ Rs. 20 Per kg 2 hours Material used Labour per unit Labour rate per hour Rs.10.00 FACTORY OVERHEADS: Fixed Rs. 10,000 Rs. 20,000 Variable ACTUAL PERFORMANCE: 900 2750 kg at Rs. 22 per kg 1850 hours at Rs. II per hour Rs. 26900 Units completed Materials used Labour hours worked FOH incurred Required: Compute Two Variance for each of the following items: (a) Materials (b) Labour (c) Factory overheads
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Variance analysis is the study of difference between planned and actual costs to ascertain business performance a Determination of Material variance 1 ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get StartedRecommended Textbook for
Understanding Basic Statistics
Authors: Charles Henry Brase, Corrinne Pellillo Brase
6th Edition
978-1133525097, 1133525091, 1111827028, 978-1133110316, 1133110312, 978-1111827021
Students also viewed these Accounting questions
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
View Answer in SolutionInn App