Following information relates to Confusion Corporation Standard or Budgeted Costs Actual Costs. Material: 5kg per unit @ $ 25 per unit Labor: 4hours per unit

Following information relates to Confusion Corporation Standard or Budgeted Costs Actual Costs. Material: 5kg per unit @ $ 25 per unit Labor: 4hours per unit @ $6 per unit.

3,000 units were made using 18,000 kg @$30 per unit and 38,000 hours were used @ $ 4.5 per hour.

Required: Calculate 1. Material Quantity Variance (MQV) 2. Material Price Variance (MPV) 3. Total material Variance or Overall Material Variance (TMV) 4. Labor Rate Variance (LRV) 5. Labor Efficiency Variance (LEV) & overall labor variance.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting Information And Equity Valuation Theory, Evidence, And Applications

Authors: Guochang Zhang

1st Edition

1461481597, 9781461481591

More Books

Students also viewed these Accounting questions