Following is a table listing the project activities, sequencing requirements and other relevant information: Expected Time Direct Cost Activity Preceded By Regular Crash Regular Crash

  • Following is a table listing the project activities, sequencing requirements and other relevant information:


Expected Time
Direct Cost
Activity
Preceded By
Regular
Crash
Regular
Crash
A
--
6 days
2 day
$2000
$3800
B
--
12
6
2000
10000
C
A
4
2
1000
4000
D
B, C
10
6
3400
4600
E
D
8
6
2800
3900
F
E
6
2
5000
7600
G
B, C
18
8
16000
19600
H
F, G
6
4
2000
4000

Construct a network including the Early and Late Start and Finish times.

Identify the normal Critical Path(s) and the normal expected completion time

Can the project be crashed to last 18 days? Which activities should be crashed and at what additional cost?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management Achieving Competitive Advantage

Authors: Jeffrey K. Pinto

4th edition

133798070, 978-0133798074

More Books

Students also viewed these Mathematics questions