Question
FoodFox Bhd is a new company that provides online food delivery services. Sarimah has been appointed as a project manager to manage a system development
FoodFox Bhd is a new company that provides online food delivery services. Sarimah has been appointed as a project manager to manage a system development project on the most convenient online food ordering site for FoodFox Bhd. She creates a project schedule and the following tasks are scheduled in sequence.
Activity
Description
Duration/Days
Predecessor
Activity/s
A
Creating project team
4
-
B
Planning the project
16
A
C
Analysis and design
19
B
D
Signing agreement with food companies as business partners
15
A
E
Purchasing domain
7
C,D
F
Hosting and back-end
4
E
G
Website design
30
E
H
Testing
9
F,G
I
Training
10
H
REQUIRED:
(a)make a PERT chart (network diagram) based on the task list above.
(7 Marks)
(b)Identify the critical path and the total days to complete the project.
(2 Marks)
(c)Identify TWO (2)activities with multiple predecessors.
(1 Mark)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started