For a particular operation, the setup time is 10 minutes, and the run time is 50 minutes to produce a standard lot of 50 parts.

  1. For a particular operation, the setup time is 10 minutes, and the run time is 50 minutes to produce a standard lot of 50 parts. It takes three additional hours to circulate a container of parts after production is completed. The demand rate is 40,000 parts per month. There are 160 production hours in a month. (1 point)

  1. How many standard containers are needed?

n = D(T) / C Use the following inputs:

Demand rate (D) = ________ parts / hour

Lead Time (L) = ________ hours

Container size (C) = ________ parts

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamentals of Management

Authors: Robbins, DeCenzo, Coulter

7th Edition

132996855, 0-13-610982-9 , 9780132996853, 978-0-13-61098, 978-0136109822

More Books

Students also viewed these General Management questions