Answered step by step
Verified Expert Solution
Question
1 Approved Answer
For a process shown below, what is the Activity Efficiency (AE) for primed flow Operation Operation Operation Operation A B C D C/T mins
For a process shown below, what is the Activity Efficiency (AE) for primed flow Operation Operation Operation Operation A B C D C/T mins 24 28 30 22 Shift time mins 480 83.7% 88.1% 72.3% 86.5% Answer is 88.1% C/T mins Operation Operation Operation Operation A B 24 28 480 C D 30 30 22 Shift time mins Total T/T (1st part) 104 AE Ideal output 18.5 units 100% Primed # in shift 16.3 units 88.1% time
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started