For a small manufacturing project consider the following : - Baseline contact value = $80,000 - Planned progress (as per schedule baseline ) = 40%

For a small manufacturing project consider the

following :

- Baseline contact value = $80,000

- Planned progress (as per schedule baseline ) = 40%

- Your Data Date @ 47.5% physical progress .

- Actual expenditure = $48,000

-

1- Calculate the required fund , assuming the same calculated projection of cost performance, that must be obtained for the remaining work (ETC)

2- Interpret schedule and cost performance for this contractor, consider KPIs = 0.90 is a Corporate target

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Clinical Work And General Management Of A Standard Minimal Resource Facility

Authors: Musa Touray, Aisha Touray

1st Edition

3030710319, 978-3030710316

More Books

Students also viewed these General Management questions

Question

What questions do you have for us?

Answered: 1 week ago

Question

a. Did you express your anger verbally? Physically?

Answered: 1 week ago