Answered step by step
Verified Expert Solution
Question
1 Approved Answer
For a small manufacturing project consider the following : - Baseline contact value = $80,000 - Planned progress (as per schedule baseline ) = 40%
For a small manufacturing project consider the
following :
- Baseline contact value = $80,000
- Planned progress (as per schedule baseline ) = 40%
- Your Data Date @ 47.5% physical progress .
- Actual expenditure = $48,000
-
1- Calculate the required fund , assuming the same calculated projection of cost performance, that must be obtained for the remaining work (ETC)
2- Interpret schedule and cost performance for this contractor, consider KPIs = 0.90 is a Corporate target
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started