For a small project of 12 activities, the details are given below. Draw the network and find earliest occurrence time, latest occurrence time, critical activities
For a small project of 12 activities, the details are given below. Draw the network and find earliest occurrence time, latest occurrence time, critical activities and project completion time. Perform a complete float analysis. The duration is in days