For any actual level of output, the difference between the input that was actually used and the input should have been used is a .
For any actual level of output, the difference between the input that was actually used and the input should have been
used is
a a purchase cost variance.
b a rate variance.
c an efficiency variance.
d an effectiveness variance.
e the variance rate.