For each of the following activities and corresponding estimated information, calculate the following information: Production rate per crew for each activity (units per crew hour)

For each of the following activities and corresponding estimated information, calculate the following information:

  1. Production rate per crew for each activity (units per crew hour)
  2. Time to complete each activity (hours)
  3. Duration of each activity (whole days, rounded up)

Activity

PIB

Production Rate (units per man-hour)

Quantity of material

(units)

Workers per crew

A or 5

None

3.125

200

2

B or 10

5

3.125

300

4

C or 15

5

3.125

200

2

D or 20

10, 15

6.250

100

1

E or 25

15

3.125

300

4

F or 30

20

6.250

100

2

G or 35

20, 25

3.125

300

3

H or 40

25

6.250

300

2

I or 45

30, 35, 40

6.250

200

2

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Modeling

Authors: Simon Benninga

3rd Edition

0262026287, 9780262026284

More Books

Students also viewed these Accounting questions

Question

What is a standard cost?

Answered: 1 week ago

Question

SB 29 Chapte 7.7 Find the answer 6.3 Ner 6/5) 3/5

Answered: 1 week ago