For each of the following activities and corresponding estimated information, calculate the following information: Production rate per crew for each activity (units per crew hour)
For each of the following activities and corresponding estimated information, calculate the following information:
- Production rate per crew for each activity (units per crew hour)
- Time to complete each activity (hours)
- Duration of each activity (whole days, rounded up)
Activity | PIB | Production Rate (units per man-hour) | Quantity of material (units) | Workers per crew |
A or 5 | None | 3.125 | 200 | 2 |
B or 10 | 5 | 3.125 | 300 | 4 |
C or 15 | 5 | 3.125 | 200 | 2 |
D or 20 | 10, 15 | 6.250 | 100 | 1 |
E or 25 | 15 | 3.125 | 300 | 4 |
F or 30 | 20 | 6.250 | 100 | 2 |
G or 35 | 20, 25 | 3.125 | 300 | 3 |
H or 40 | 25 | 6.250 | 300 | 2 |
I or 45 | 30, 35, 40 | 6.250 | 200 | 2 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started