Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

For May, Mariana company planned production of 10,000 units (80% of its production capacity of 12,500 units) and prepared the following overhead budget. The company

For May, Mariana company planned production of 10,000 units (80% of its production capacity of 12,500 units) and prepared the following overhead budget. The company applies overhead with a standard of 2 DLH per unit and a standard overhead rate of $4 per DLH.

Overhead Budget 80% Operating Level
Production (in units) 10,000
Budgeted overhead
Variable overhead costs
Indirect materials $ 15,000
Indirect labor 20,000
Power 5,000
Maintenance 2,000
Total variable overhead costs 42,000
Fixed overhead costs
Rent of building 15,000
DepreciationMachinery 11,200
Supervisory salaries 9,800
Total fixed overhead costs 36,000
Total overhead $ 78,000

It actually operated at 90% capacity (11,250 units) in May and incurred the following actual overhead.

Actual Overhead Costs
Indirect materials $ 15,000
Indirect labor 22,400
Power 5,625
Maintenance 3,050
Rent of building 15,000
DepreciationMachinery 11,200
Supervisory salaries 12,500
Actual total overhead $ 84,775

1. Compute the overhead controllable variance and identify it as favorable or unfavorable. 2. Compute the overhead volume variance and identify it as favorable or unfavorable. 3. Prepare an overhead variance report at the actual activity level of 11,250 units.

Complete this question by entering your answers in the tabs below.

  • Required 1
  • Required 2
  • Required 3

Compute the overhead controllable variance and identify it as favorable or unfavorable. (Indicate the effect of the variance by selecting favorable, unfavorable, or no variance.)

Controllable variance
Actual total overhead $84,775selected answer correct
Budgeted (flexible) overhead
Variable overheadselected answer correct $47,250selected answer correct
Fixed overheadselected answer correct 36,000selected answer correct 83,250
Controllable variance $1,525selected answer correct Unfavorableselected answer correct

Compute the overhead volume variance and identify it as favorable or unfavorable. (Indicate the effect of the variance by selecting favorable, unfavorable, or no variance. Do not round intermediate calculations.)

Volume Variance
Budgeted (flexible) overheadselected answer correct $83,250selected answer correct
Standard overhead appliedselected answer correct 40,500selected answer incorrect
Volume variance $42,750selected answer incorrect Favorableselected answer correct

Prepare an overhead variance report at the actual activity level of 11,250 units. (Indicate the effect of each variance by selecting favorable, unfavorable, or no variance. Do not round intermediate calculations.)

MARIANA COMPANY
Overhead Variance Report
For Month Ended May 31
Expected 80% of capacityselected answer correct
Actual 90% of capacityselected answer correct
Volume variance $42,750selected answer incorrect Favorableselected answer correct
Controllable Variance Flexible Budget Actual Results Variances Favorable/Unfavorable
Variable overhead costs:
Indirect materialsselected answer correct $16,875selected answer correct $15,000selected answer correct $1,875selected answer correct Favorableselected answer correct
Indirect laborselected answer correct 22,500selected answer correct 22,400selected answer correct 100selected answer correct Favorableselected answer correct
Powerselected answer correct 5,625selected answer correct 5,625selected answer correct 0selected answer correct No varianceselected answer correct
Maintenanceselected answer correct 2,250selected answer correct 3,050selected answer correct 800selected answer correct Unfavorableselected answer correct
not attempted not attempted not attempted not attempted not attempted
Total variable overhead costsselected answer correct 47,250 46,075 1,175selected answer correct Favorableselected answer correct
Fixed overhead costs:
Rent of buildingselected answer correct 15,000selected answer correct 15,000selected answer correct 0selected answer correct No varianceselected answer correct
DepreciationMachineryselected answer correct 11,200selected answer correct 11,200selected answer correct 0selected answer correct No varianceselected answer correct
Supervisory salariesselected answer correct 9,800selected answer correct 12,500selected answer correct 2,700selected answer correct Unfavorableselected answer correct
not attempted not attempted not attempted not attempted not attempted
Total fixed overhead costsselected answer correct 36,000 38,700 2,700selected answer correct Unfavorableselected answer correct
Total overhead costs $83,250 $84,775 $1,525selected answer correct Unfavorableselected answer correct
Volume Variance
Budgeted (flexible) overheadselected answer correct 83,250selected answer correct
Standard overhead appliedselected answer correct 40,500selected answer incorrect
Volume variance $42,750selected answer incorrect Favorableselected answer correct
Total overhead variance not attempted Favorableselected answer correct

**** Having trouble figuring out the Standard overhead applied amount and volume variance for required two.

***** Having trouble figuring out bottom portion of required three for standard overhead applied, volume variance, and total variance.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The Sixth International Congress On Accounting 1952

Authors: Various

1st Edition

0367512807, 9780367512804

More Books

Students also viewed these Accounting questions

Question

What would you do about the verbal homophobic insults?

Answered: 1 week ago