For problems 1 to 5 use the following table (time in days): Activity Preceeding Activity Time ES EF LS LF A 0 6 42 48

image text in transcribed

image text in transcribed
For problems 1 to 5 use the following table (time in days): Activity Preceeding Activity Time ES EF LS LF A 0 6 42 48 B 18 18 18 C 4 4 30 34 D B 30 18 48 18 48 E A.D 4 48 52 18 $2 F C 18 4 22 34 52 G E, F 24 52 76 52 76 1. Which of the statements is true about activity F: A) Maximum number of days required to complete activity F without delaying the project is 52 days B) Activity F must be started by day 4 in order not to delay the project C) Activity F is on the critical path D) Activity F cannot be started unless activities A, B, C, D, and E are completed. 2. What is the slack time for activity C: 3 3. The activities that constitute the critical path are: A) ADEG B) BGH C) BDEG D) None of the above

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Management Theory And Practice

Authors: Eugene Brigham, Michael Ehrhardt, Jerome Gessaroli, Richard Nason

3rd Canadian Edition

017658305X, 978-0176583057

More Books

Students also viewed these Finance questions

Question

HOW DOES PROCESS COSTING DIFFER FROM JOB ORDER COSTING? LO.1

Answered: 1 week ago