Answered step by step
Verified Expert Solution
Link Copied!

Question

00
1 Approved Answer

For questions 3 and 4 , do the following. ( a ) Construct an activity network for the preceedance tables. [ 3 ] ( b

For questions 3 and 4, do the following.
(a) Construct an activity network for the preceedance tables. [3]
(b) Calculate the event times (earliest start times and latest start times), and
hence find the critical path. [6]
(c) Calculate the total, independent and interfering float times, for each activity. [12]
(d) Give a critical path. [2]
3.
Activity Duration Immediate
Predecessors
A 7-
B 6-
C 8-
D 4 A
E 5 A
F 9 B, E
G 3 B, E
H 2 C
I 4 D, F
J 3 H
4.
Activity Duration Immediate
Predecessors
A 3-
B 8-
C 4-
D 3 A
E 7 B, C
F 5 B, C
G 3 D
H 8 D
I 3 E, G
J 8 F
K 2 J

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Marketing Management

Authors: Mark Johnston, Greg Marshall

3rd edition

1259637158, 978-1259637155

Students also viewed these General Management questions