For risks that have a high probability and impact, the project team should definitely __________. A. Set aside contingency reserves B. Plan a response strategy
For risks that have a high probability and impact, the project team should definitely __________. A. Set aside contingency reserves B. Plan a response strategy C. Alert senior management D. Identify triggers