For risks that have occurred in a project, the team should Group of answer choices add more resources to the tasks that are impacted by
For risks that have occurred in a project, the team should
Group of answer choices
add more resources to the tasks that are impacted by the risk occurring.
expect that the other risks are going to occur so they should increase resources for those tasks impacted.
track and document the risks and store the information in lessons learned.
talk about the risk without recording the minutes of the meeting.