For the following process, management has hired a new worker for station B. The new hire works at a cycle time (CT) of 10 mins
For the following process, management has hired a new worker for station B. The new hire works at a cycle time (CT) of 10 mins per unit. What is the new capacity of station B in units per hour after adding the new hire? Enter your answer rounded to 2 decimal places. (New hire is not shown in the process diagram below. The new hire is the only addition and no workers are removed.)
StationA1worker,working@CT:6min/unitCT:4min/unitStationBCT:8min/unitCT:5min/unitStationC1worker,working@worker,working@StationD1worker,working@Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started