For the following questions refer to the figure below a. Complete the missing data in the table below. b . What is the cost index?

For the following questions refer to the figure below
a. Complete the missing data in the table below.
b . What is the cost index? The schedule index?
Give your comments about the project performance

 

J M V Y XOH 2 4 6 8 9 Scheduled activity % complete 1 10 11 12 13 34 Data date=13 weeks 15 16 17 15 19 20 Activity on the critical path 21 22 23 24 25 26 Budget at completion($) Scheduled J: $31,362 100 M:$138,571 ? V: $20,945 Y:$20,352 % W:$4,235 50 L:$21,272 ? X:$6,622 BAC= $344,205 0 Q:$100,846 ? 0 0 Status after 13 weeks BCWS % Completed 31,362 ? ? 0 ? ? 0 0 Total BCWS=? 100 100 33 0 ? ? 0 ? BCWP 31,362 ? ? 0 ? ? 0 0 Total BCWP=? ACWP 30,550 155,180. 8,933 0 20,644 ? ? ? Total ACWP= $288,657

Step by Step Solution

3.47 Rating (157 Votes )

There are 3 Steps involved in it

Step: 1

To complete the missing data in the table lets address each item systematically using information available from the chart For activity M The Schedule... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction to graph theory

Authors: Douglas B. West

2nd edition

131437372, 978-0131437371

More Books

Students also viewed these General Management questions

Question

What are the factors affecting organisation structure?

Answered: 1 week ago

Question

What are the features of Management?

Answered: 1 week ago

Question

Briefly explain the advantages of 'Management by Objectives'

Answered: 1 week ago