For the following questions, utilize the project data below. Assume all tasks start on the same day. TASKS AB takes 7 days TASK C takes
For the following questions, utilize the project data below. Assume all tasks start on the same day.
TASKS AB takes 7 days
TASK C takes 9 days
TASKS DEF takes 8 days
TASKS DGH takes 10 days
a)What is the critical path for this project?
b)Define Slack Time? (i.e. Explain what it is)
c) What is the slack time for C?
d) What is the slack time for A?
e) What is the slack time for G?