For the following table of information, 1. Draw the network diagram 2. List the network paths 3. Determine the critical path(s) 4. Determine the float
For the following table of information, 1. Draw the network diagram 2. List the network paths 3. Determine the critical path(s) 4. Determine the float for each activity Activity Duration Dependency Float Start 0 days A 5 days Start B 2 days Start C 3 days A, B D 5 days Start E 6 days Start T1 4 days D, E G 2 days C, F H 5 days G - 7 days G L 3 days H Finish 0 days 1, J