Question
1 Approved Answer
For the next question, consider the following information: Accounts receivable, 12/31/2018 (from construction progress billings) $37.5 Actual construction costs incurred in 2018 $135 Cash collected
For the next question, consider the following information:
Accounts receivable, 12/31/2018 (from construction progress billings) | $37.5 |
Actual construction costs incurred in 2018 | $135 |
Cash collected on project during 2018 | $105 |
Construction in progress, 12/31/2018 | $207 |
Estimated percentage of completion during 2018 | 60% |
In 2018, Cupid Construction Co. (CCC) began work on a two-year fixed price contract project. CCC recognizes revenue over time according to percentage of completion for this contract, and provides the following information (dollars in millions):What is the amount of gross profit on the project recognized by CCC during 2018?
a. | $48 million | |
b. | Cannot be determined from the given information. | |
c. | $160 million | |
d. | $72 million |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started