Question

1 Approved Answer

For the planning of the project, the following has been done: A list of activities has been made, and for each activity optimistic, pessimistic, and

For the planning of the project, the following has been done: A list of activities has been made, and for each activity optimistic, pessimistic, and most likely time estimates have been collected. Based on these estimates, an average expected activity time and a variance for that time have been computed. A sketch has been made to show the order and dependencies of the activities in this project. The total cost of the project is estimated between $130,000 and $137,000.
This is the data: (all times in days).

\( \begin{array}{lrr}\text { Activity } & \text { estimated } & \text { variance } \\ \text { A } & \text { Time } & \text {

a) Compute the probability that this project is finished within the 24 days deadline.
b) It is possible to speed up activity B: finishing it within 12 days would bring an extra cost of $4,000. It is also possible to speed up activity E, finishing this in 3 days would bring an extra cost of $2,000. Based on this information, give motivated advice on speeding up the project.
 

estimated Time 12 18 [] 8 6 5 3 15 Activity A B CDEFG A variance B C E time 16 18 4 2.25 1.8 1 8 G (F D

Step by Step Solution

3.30 Rating (150 Votes )

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Quantitative Analysis For Management

Authors: Barry Render, Ralph M. Stair, Michael E. Hanna

11th Edition

9780132997621, 132149117, 132997622, 978-0132149112

More Books

Students also viewed these General Management questions

Question

Explain how and when to modify the marketing plan.

Answered: 1 week ago

Question

If M = 7, s = 2, and X = 9.5, what is z?

Answered: 1 week ago