For the precedence network diagrams listed below, determine the following values for each activity: (1 point for each answer) The earliest start time Earliest finish
- For the precedence network diagrams listed below, determine the following values for each activity: (1 point for each answer)
- The earliest start time
- Earliest finish time
- Latest finish time
- Latest start time
- Activity slack time
- Identify the critical activities
- Determine the duration of the project