Question
For the solution of Why is the answer for finished goods equal 0? Shouldn't that be $60,000 from Job 612 which is completed? Fulton Construction
For the solution of
Why is the answer for finished goods equal 0? Shouldn't that be $60,000 from Job 612 which is completed?
Fulton Construction
Fulton Construction company uses a job order costing system and applies overhead using normal
costing system based on direct labor dollars.
On December 1, it had two jobs in finished goods
inventory and two jobs in its work-in-process inventory, as follows:
Job No.
Costs as of 12/1
Status
612
60,000
Completed
613
85,000
Completed
614
45,000
In-process
615
18,000
In-process
Selected data for the month of December follow:
1.
Direct materials issued: Job 614: $13,000; Job 615: $8,000; Job 616: $12,000
2.
Direct labor costs: Job 614: $20,000; Job 615: $42,000; Job 616: $5,000
3.
Applied overhead: Job 614: $14,000; Job 615: $29,400; Job 616: $3,500
4.
Actual overhead costs incurred: $50,000
5.
Completed Job 614.
Did not complete Jobs 615 and 616.
6.
Sold Jobs 613 and 614.
Questions:
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started