Question
For this week, you will do a communications plan for your selected project.The first step in developing your communication plan is figuring out what kind
For this week, you will do a communications plan for your selected project.The first step in developing your communication plan is figuring out what kind of communication your stakeholders need from the project so they can make good decisions. This information can be drawn from the stakeholder register and also by interviewing each stakeholder. Methods of communication can take on many forms, such as written reports, conversations, email, formal status reports, meetings, and online resources; hence, there is no such thing as a "one size fits all" approach especially when there may be time zone differences.
All projects require a sound communication plan, but not all projects will have the same types of communication nor the same methods for distributing project information. The types of information that are typically communicated include project status, project scope statements and updates, project baseline information, risks, issues, action items, performance measures, project acceptance, and RAG rating.
This is the project charter i used.
PROJECT CHARTER
Part I: Project Overview
Project Name | On-Site Childcare Program | ||
Charter Author | |||
Creation Date | 05/19/2023 | Last Revised | |
Project Sponsor | Leslie Hamm, Director | Project Manager | |
Targeted Start & End Date | 05/21/23 to 06/25/23 | Project Approval Date | 05/25/2023 |
Part II: Project Details
Executive Summary | The objective of this project is to create a separate area where the employees' children can be looked after. The goals are to enable workers to have trusted personnel and a secure area for their children. Also, to allow workers to have their children near them, which in turn will help the company control absenteeism and lateness better. This project will help with productivity as workers will feel more at peace knowing that they have reliable childcare and that their children are close by. | ||||||||||||||||||||||||||||||||||||||||||
Problem Statement | The problem that we have now is that many employees have difficulty finding reliable or affordable childcare. This in turn causes them to use more time off, be late for work, or leave early. This problem needs to be resolved to have better morale and productivity in the company. | ||||||||||||||||||||||||||||||||||||||||||
Business Rationale | The high-level benefits of having an on-site childcare program are:
* How on -site childcare companies are changing the workplace - https://www.brighthorizons.com/benefits/onsite-child-care-benefits#:~:text=On%2Dsite%20child%20care%20companies%20help%20employers%20provide%20quality%2C%20affordable,more%20fully%20on%20their%20jobs. | ||||||||||||||||||||||||||||||||||||||||||
Strategic Alignment |
| ||||||||||||||||||||||||||||||||||||||||||
Goals & Objectives | Goals: Describe the high-level goals of the project. Often these goals can be categorized by People, Process or Technology. Objectives: For each goal, describe the project objectives that will be met to support achieving the goal. Objectives may support multiple goals, but only need to be listed once. An objective should follow the SMART criteria: specific, measurable, achievable, relevant, time bound. Deliverables: For each objective, describe the deliverables that will be produced by the project team by the time the project completes. Embedded commentary is for example purposes ONLY.
| ||||||||||||||||||||||||||||||||||||||||||
Project Model | The following are the models that will be leveraged throughout the life of the project.
| ||||||||||||||||||||||||||||||||||||||||||
Project Life Cycle & Development Approach | This project will begin with the design and remodeling of the office spaces to become a childcare center. This will involve construction workers. Once the center is created, the equipment and furnishings will need to be installed. Personnel will need to be trained. Meetings will need to be conducted to see the progress made, situations that may not be working, and implementation of changes. | ||||||||||||||||||||||||||||||||||||||||||
Scope | Inclusions | Exclusions | |||||||||||||||||||||||||||||||||||||||||
The on-site childcare program will be situated in the offices towards the right of the entrance in the company's building. This childcare program will benefit employees of the company only. The program will cut into unnecessary time used by the employees thus, saving the company money. Employees will have the opportunity to apply to be considered to fill the childcare positions. | All areas of the company that do not have a direct impact on the project will be excluded such as the production department, the service department, and the quality control department. Also, all data programs needed to run the production and service departments. | ||||||||||||||||||||||||||||||||||||||||||
Stakeholders | Name | Role | |||||||||||||||||||||||||||||||||||||||||
Leslie Hamm, Director Maria Centeno Michael Swabb Louise Quinn Matthew Sharp Charlie May Kent Smith Rosie DeRios | Project Sponsor Project Manager Team Member - Supervisor of childcare personnel Team Member - Supervisor of technology personnel Office space redesign - independent contractor Trainer childcare personnel - independent contractor Team member - Supervisor of security personnel Construction - independent contractor | ||||||||||||||||||||||||||||||||||||||||||
Resources | Internal | External | |||||||||||||||||||||||||||||||||||||||||
|
| ||||||||||||||||||||||||||||||||||||||||||
Project Risks | Insert a list of initial project risks that have been identified. Risks affecting your project may relate to some of the following types: Leadership level support, scope definition, cost forecasts, change management, stakeholder support, communication, resources, technology, integration, requirements, decision process, issue resolution, procurement, approvals, user acceptance, market, or other external risks. Embedded commentary is for example purposes ONLY.
| ||||||||||||||||||||||||||||||||||||||||||
Known Constraints | The factors that may limit the ability of the project to be successful or to execute effectively could be:
| ||||||||||||||||||||||||||||||||||||||||||
Project Dependencies | The project is reliant upon government agencies which will be providing permits and licenses. Also, it is reliant upon the independent contractors hired to complete remodeling office space into the childcare site and to provide training to the employees that will be working in the childcare. | ||||||||||||||||||||||||||||||||||||||||||
Assumptions |
| ||||||||||||||||||||||||||||||||||||||||||
Key Deliverables | Name | Description | |||||||||||||||||||||||||||||||||||||||||
|
| ||||||||||||||||||||||||||||||||||||||||||
Cost | Insert a list of high-level costs associated with project delivery. This may include capital costs, operational costs, direct costs, indirect costs, labor, materials, or travel costs depending on the nature of the project. Embedded commentary is for example purposes ONLY.
| ||||||||||||||||||||||||||||||||||||||||||
Benefits | Insert a list of high-level benefits this project will deliver. This may include additional revenue realized, cost savings, time savings, efficiencies for the organization, customer satisfaction or improved productivity depending on the goals and objectives of the project. Where possible, it is encouraged to assign a monetary value to each benefit to effectively compare costs and benefits. Embedded commentary is for example purposes ONLY.
| ||||||||||||||||||||||||||||||||||||||||||
Success Criteria |
| ||||||||||||||||||||||||||||||||||||||||||
Roles & Responsibilities | List roles and responsibilities for roles that may or may not be part of your project. It is recommended that the responsibilities identified here are reviewed with the team members filling these roles to ensure that clear expectations are set, and any gaps are identified. Embedded commentary is for example purposes ONLY.
| ||||||||||||||||||||||||||||||||||||||||||
Part III: High Level Project Milestone Summary
It is recommended that a separate and detailed project schedule is documented to identify and manage all project related activities utilizing the Project Team's tool of choice (MS Project, MS PowerPoint, Excel, Kanban, etc.). List high-level (Level 1) project milestones in this section.
Milestone | Start Date | End Date | Dependencies |
Getting approval for project from project sponsor | 05/21/2023 | 05/25/2023 | Mandatory |
Redesigning Office Space | 05/26/2023 | 06/12/2023 | External |
Installing Technology | 06/13/2023 | 06/16/2023 | Discretionary |
Training personnel | 06/16/2023 | 06/22/2023 | Internal |
Review and completion of project (opening of on-site childcare center) | 06/23/2023 | 06/26/2023 | Internal |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started