For which contract does the buyer pay the supplier for allowable performance costs plus a fixed fee payment usually based on a percentage of estimated
For which contract does the buyer pay the supplier for allowable performance costs plus a fixed fee payment usually based on a percentage of estimated costs? a. Cost Plus Fixed Fee b. Fixed-Price Incentive Fee c. Cost Plus Award Fee d. Cost Plus Incentive Fee