Forgery Company make two products, titanium Hubs and sprocket. Data regarding the two products follow: Direct Labor-Hours per Unit Annual Production Hubs 0.8 10,000 units
Forgery Company make two products, titanium Hubs and sprocket. Data regarding the two products follow:
| Direct Labor-Hours per Unit | Annual Production |
Hubs | 0.8 | 10,000 units |
Sprockets | 0.40 | 40,000 units |
Additional information about the company follows:
Hubs require #32 in direct material per unit, and sprockets require $18.
The direct labor wage rate is $15 per hour
Hubs are more complex to manufacture than sprockets and they require special equipment.
The ABC system has the following activity cost pools:
Activity
Activity Cost Pool (activity measure) | Estimated Overhead Cost | Hubs | Sprocket | Total |
Machine setups (number of setups | $72,000 | 100 | 300 | 400 |
Special processing (machine-hours) | $200,000 | 5,000 | 0 | 5,000 |
General factory (organization sustaining) | $816,000 | NA | NA | NA |
Required
Compute the activity rate for each activity cost pool. Did you compute an activity rate for all of the activity cost pool? Why?
Determine the unit product cost of each product according to the ABC system.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started