Question
Formulas provided by professor: EOQ=2DSHEOQ=2DSH TC=SDQ+HQ2TC=SDQ+HQ2 PurchasingCost=PD SigmaLTD=SQRT(L)*SigmaR SigmaLTD=R*SigmaL SL*=Cu/(Cu+Co) RT=I Rp=c/Tp Cycle Time = CT=1/Rp Takt Time = TT= 1/R Cycle Inventory = Q/2
Formulas provided by professor:
EOQ=2DSHEOQ=2DSH
TC=SDQ+HQ2TC=SDQ+HQ2
PurchasingCost=PD
SigmaLTD=SQRT(L)*SigmaR
SigmaLTD=R*SigmaL
SL*=Cu/(Cu+Co)
RT=I
Rp=c/Tp
Cycle Time = CT=1/Rp
Takt Time = TT= 1/R
Cycle Inventory = Q/2
Average Inventory in the Presence of Safety Stock = Cycle Inventory +Isafety
Question:
QUESTION 1:
Auto-Moto receives about 450 loan applications per month (30 working days). All applications go through an Initial Review sub-process, where the applications are then classified as A (looks excellent), B (needs more detailed evaluation), and C (reject summarily). A and B applications would be forwarded to sub-processes A and B, respectively. On average, 10% of all applications go through Sub-process A, 50% go through sub-process B, and the rest are rejected. On average, 50% of applications in sub-process A, and 10% of applications in sub-process B are accepted and the rest are rejected. (Recall that all Cs were rejected.) On average 99 applications are in the Initial Review sub-process, 21 are in sub-process A, and 72 applications are in sub-process B.
1a. How many applications are rejected per month? The potential answers are:
A: 419 applications.
B: 430 applications.
C: 370 applications.
D: 405 applications.
E: 473 applications.
1b. What is the average flow time of an application? The potential answers are:
A: 12.6 days.
B: 12 days.
C: 7.68 days.
D: 12.8 days.
E: 9.15 days.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started