Formulate a realistic Schedule Baseline for a project to build a software program to monitor cameras on stoplight across Jamaica. Use a Gantt chart and
Formulate a realistic Schedule Baseline for a project to build a software program to monitor cameras on stoplight across Jamaica. Use a Gantt chart and a schedule baseline chart to show the activity/schedule management plan. Duration of the project is 24 weeks.
example below of a schedule baseline for a different project as a guide
Schedule Baseline
Task | Duration | Start Date | End Date | |||
Project Management | 16 days | May 15, 2023 | May 31, 2023 | |||
Completion & signing of Project Charter | 5 | May 15, 2023 | May 20, 2023 | |||
Formation of Project team | 3 | May 21, 2023 | May 24, 2023 | |||
Creation of Project Management Plan | 3 | May 25, 2023 | May 28, 2023 | |||
Arrange meetings with Project Sponsor and Stakeholders | 2 | May 29, 2023 | May 31, 2023 | |||
Land Preparation | 16 days | May 30, 2023 | June 15, 2023 | |||
Design of Park Beautification | 4 | May 30, 2023 | June 03, 2023 | |||
Approval of Layout Design of Park Beautification by sponsor | 1 | June 03, 2023 | June 04, 2023 | |||
Approval of Layout Design of Park Beautification by Portmore Municipal Council | 2 | June 05, 2023 | June 07, 2023 | |||
Permit granted by NEPA | 3 | June 08, 2023 | June 11, 2023 | |||
Project approved | 1 | June 11, 2023 | June 12, 2023 | |||
Clear Land | 3 | June 12, 2023 | June 15, 2023 | |||
Procurement | 15 days | May 20, 2023 | June 04, 2023 | |||
Prepare RFT | 1 | May 20, 2023 | May 21, 2023 | |||
Advertise RFT | 3 | May 21, 2023 | May 24, 2023 | |||
Evaluate bids (suppliers) | 2 | May 24, 2023 | May 26,2023 | |||
Select supplier | 1 | May 26, 2023 | May 27, 2023 | |||
Enter into contract supplier | 3 | May 27, 2023 | May 30, 2023 | |||
Purchase of Equipment | 3 | May 31, 2023 | June 03, 2023 | |||
Purchase of Materials and Resources | 4 | May 31, 2023 | June 04, 2023 | |||
Purchase of Plants (trees, flowers, grass seeds and sod) | 3 | June 01, 2023 | June 04, 2023 | |||
Purchase of Topsoil | 1 | June 03, 2023 | June 04, 2023 | |||
Landscaping | 147 days | June 06, 2023 | Oct 31, 2023 | |||
Measure and Dig Holes for Plants | 14 | June 06, 2023 | June 20, 2023 | |||
Plant Trees (large) | 17 | June 06, 2023 | June 23, 2023 | |||
Plant Trees (small) | 28 | June 24, 2023 | July 22, 2023 | |||
Flowers Plant | 27 | July 22, 2023 | Aug 18, 2023 | |||
Prep Land Space for Lawn Grass | 13 | Aug 18, 2023 | Aug 31, 2023 | |||
Layout lawn grass (sod) | 2 | Aug 31, 2023 | Sep 02, 2023 | |||
Add decorative stones around tress | 14 | Sep 02, 2023 | Sep 14, 2023 | |||
Add mulch around trees and flowers | 14 | Sep 14, 2023 | Sep 28, 2023 | |||
Final trim and cut of edges | 21 | Sep 28, 2023 | Oct 19, 2023 | |||
Clear park of debris | 5 | Oct 19, 2023 | Oct 24, 2024 | |||
Approval and sign off by Sponsor | 2 | Oct 25, 2023 | Oct 27, 2023 | |||
Project Complete | 0 | Oct 28, 2023 | Oct 28, 2023 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started