Question
1 Approved Answer
Forward Venture Company, which uses a standard cost system, budgeted $602,000 of fixed overhead when 43,000 machine hours were anticipated. Other data for the period
Forward Venture Company, which uses a standard cost system, budgeted $602,000 of fixed overhead when 43,000 machine hours were anticipated. Other data for the period were: Actual units produced: 12,000 Standard production time per unit: 3.2 machine hours Fixed overhead incurred: $622,000 Actual machine hours worked: 46,000 Forward Venture Company's fixed-overhead budget variance is