( FR ) The Actual Costs ( AC ) to date are $ 1 2 , 0 0 0 and the Budget at Completion (

(FR) The Actual Costs (AC) to date are $12,000 and the Budget at Completion (BAC) for a project is $60,000. The Earned Value (EV) is $9,000. At this stage, the project management team did a manual bottom-up summation of costs and forecast an Estimate to Complete (ETC) of $54,000. What is the Estimate at Completion (EAC) for the project?
Question 1 options:
a)
$72,000
b)
$66,000
c)
$80,000
d)
$63,000

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic Brand Management

Authors: Alexander Chernev

3rd Edition

193657263X, 9781936572632

More Books

Students also viewed these General Management questions